| No |
Targets for fiscal 2006 |
Results from fiscal 2006 |
Achievement |
| 1 |
Reduction of energy consumption Sales amount basic unit 10% reduction (BM FY2005) |
10.45% reduction
Inverter of the cooling tower, the aeration cooling of the compressor, the disposal of surplus facilities, the air conditioning stop adjustment of the holiday |
○ |
| 2 |
Resource saving by product miniaturization and the defectiveness rate reduction |
The miniaturization of the product carries out trial manufacture / evaluation premeditatedly. The defectiveness rate reduction by the production process is improvement action enforcement. |
○ |
| 3 |
Reduction of water consumption 5% reduction (BM FY2005) |
18.82% reduction The resin update of the pure water playback equipment, efficiency inflection of the plating water closet water. |
○ |
| 4 |
Reduction of waste discharge 5% reduction (BM FY2005) |
We are unachieved by the increase of the plating waste fluid, the discharge increase of the abolished waste. |
× |
| 5 |
The development promotion of the eco-friendly type product |
About the technology development of the plating solution, we completed a theme after trial and error. |
○ |
| 6 |
Reduction of hazardous substances consumption |
Reduction of hazardous substances in article: 50% reduction (achieved) Hazardous substances in production line: Consumption grasp system completion |
○ |
| 7 |
The total abolition of the PFC atmosphere discharge The 1% reduction of the VOC atmosphere discharge (BM FY2006) |
PFC: We were not able to achieve it, but expectation of the achievement was possible in FY2007. VOC: Maybe 1% reduction |
○ |
| 8 |
The formation of the tree planting to be able to get close to employees, visitor, neighborhood |
We increase the healing areas. We push forward maintenance for long-term designs of a rosary, the flower area of Sabae-shi. |
○ |
| 9 |
Enforcement of the community contribution activity |
Participation to the local beautification activity. Exhibition to Sabae-shi environment fair and the Tannan industry fair. The enforcement of the plant tour for Sabae-shi ISO network members. |
○ |
| 10 |
Introduction and step-by-step inflection of EMS software "AMRI" |